The contract is for the new striping on the Santa Ana River Trail from PCH to MacArthur. The scope of work includes applying traffic paint, cutting edges, excavating, and hauling off broken and deteriorated asphalt, as well as preparing the subgrade and applying a tack coat. The contract amount is $59,685, and the time allotted for construction is 120 calendar days. The contractor is required to pay the stipulated prevailing wage rates and submit certified payroll upon request. The contract also includes provisions for payments, changes, termination, and dispute resolution.
• The contract is for a construction project in California.
• The scope of work includes striping, asphalt repair, and subgrade preparation.
• The contract amount is $59,685.
• The time allotted for construction is 120 calendar days.
• The contractor is required to pay prevailing wage rates and submit certified payroll.
• The contract includes provisions for payments, changes, termination, and dispute resolution.