The McCourtney Road Transfer Station Improvement Project involves the expansion of the site entrance road, installation of new scale facilities, construction of a material recovery facility, and other improvements. The project is estimated to cost $19,580,000 and is subject to the payment of prevailing wages. The contract will be awarded to the lowest responsible bidder whose proposal complies with the specified requirements.
• The project includes the construction of a 48,000 square foot material recovery facility and the conversion of the existing PRA building to serve as the organics receiving and transfer building.
• The project requires the installation of approximately 170,000 square feet of new or repaved asphalt surfaces, fencing, and other circulation improvements.
• The project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
• The contract requires the contractor to possess a valid Class B General Building Contractor's License issued by the State of California.
• The contract includes a bid bond for bids over $25,000 and requires the contractor to provide a payment bond and a faithful performance bond in an amount equal to 100% of the contract price.