The Q-184 Pump Station No. 11 and Olde Eight Trunk Sewer Improvement Project involves the construction of a new sewer line and the improvement of the existing pump station. The project includes the installation of approximately 3,064 linear feet of 12-inch diameter SDR-35 PVC sanitary sewer, as well as the relocation of the existing pump station force main. The project also includes the upgrade of the pump station, including the installation of an emergency backup generator and the replacement of the existing control panel. The project is expected to be completed within 150 calendar days after the notice to proceed. The contract was awarded to 1127 Construction Inc, and the estimated value of the contract is $747,000.
• The project involves the construction of a new sewer line and the improvement of the existing pump station.
• The project includes the installation of approximately 3,064 linear feet of 12-inch diameter SDR-35 PVC sanitary sewer.
• The project also includes the upgrade of the pump station, including the installation of an emergency backup generator and the replacement of the existing control panel.
• The project is expected to be completed within 150 calendar days after the notice to proceed.
• The contract was awarded to 1127 Construction Inc.
• The estimated value of the contract is $747,000.