The contract is for the development of a water well and solar array at the Soda Lake Wildlife Habitat Management Area in Wyoming. The project involves supplying labor, materials, and equipment to develop the existing water well and install a solar array for powering the well. The contract was awarded to Water's Edge Services for a total bid amount of $36,650.00. The project duration is approximately 3 months, and the completion date is between July 15, 2023, and October 15, 2023.
• The contract is for a specific project in Wyoming.
• The project involves the development of a water well and solar array.
• The contract was awarded to Water's Edge Services.
• The total bid amount is $36,650.00.
• The project duration is approximately 3 months.