The City of Wilmington is seeking a qualified contractor to demolish the existing pier serving the Best Western Plus Coastline Inn and to restore the site. The work includes utility disconnects, removal of timber and steel structural elements, disposal of debris (including hazardous materials), installation of erosion‑control measures, back‑filling, and placement of a new concrete pad. The contract is awarded through a full and open Request for Bid, with a firm‑fixed‑price arrangement, a 90‑day performance window, and a $250 per day liquidated‑damage clause. The City requires a 14 % MWBE subcontracting effort and extensive safety, environmental, and documentation compliance.
• Demolition of pier (timber/steel), utility removal, concrete pad replacement.
• Required erosion‑control (turbidity curtains, debris booms) and site restoration (grading, seeding).
• MWBE subcontracting minimum 14 %, 90‑day schedule, $250/day liquidated damages, 1‑year warranty.