The contract is for the installation of an emergency generator and automatic transfer switch (ATS) at the Marriott Sewage Pump Station. The contract was awarded to Paul's Electrical Contracting, LLC. for a total sum of $207,700.00. The contract includes the furnishing and paying for all materials, labor, transportation, tools, equipment, machinery, and services necessary to construct or install the emergency generator and ATS. The contract also requires the contractor to submit a performance and payment bond, as well as insurance as required per solicitation or negotiation.
• The contract is for a lump sum of $207,700.00.
• The contractor is required to submit a performance and payment bond.
• The contractor is required to submit insurance as required per solicitation or negotiation.
• The contract includes the furnishing and paying for all materials, labor, transportation, tools, equipment, machinery, and services necessary to construct or install the emergency generator and ATS.
• The contract is expected to start after the "Notice To Proceed" is issued.