The contract is for the Sewer Lateral 19-17 project, which includes work such as erosion control, traffic control, installation of clean outs on an existing side sewer lateral, and restoration of public right of way and private property. The contract was awarded to multiple vendors, including Harkness Construction, LLC, Core Infrastructure Services, R.W. Scott Construction, NPM Construction, Northwest Cascade, Gary Thayer Construction, and Earthwork Solutions, LLC. The bid tabulation section lists the prices and quantities for each item, with a total contract value of over $150,000.
• The project includes installation of 2 clean outs on an existing side sewer lateral
• The project includes restoration of public right of way and private property
• The contract was awarded to multiple vendors
• The total contract value is over $150,000