This contract is for the repair and upgrade of the sanitary sewer collection system within the City of Rockford, Illinois, under the Rock River Water Reclamation District’s Capital Project No. 2254. The work includes replacing aging sewer mains, installing new precast concrete manholes, excavating rock, providing temporary bypass pumping, dewatering, and restoring all disturbed roadways, curbs, sidewalks, and landscaping. The project must be completed by October 31 2021 and carries a liquidated‑damage penalty of $300 per day for late completion. The contract is awarded as a lump‑sum price to Stenstrom Excavation & Blacktop Group, with a 5 % bid bond requirement and a 100 % performance bond required after award. Compliance with Illinois prevailing‑wage, ADA, OSHA, and environmental regulations is mandatory.
• Scope: sanitary sewer pipe replacement, manhole installation, rock excavation, temporary pumping, dewatering, and full pavement restoration.
• Geography: multiple public right‑of‑way locations across Rockford (maps 1‑21).
• Key dates: bid due June 24 2021, project completion deadline Oct 31 2021, liquidated‑damage $300/day.
• Vendor: single‑award to Stenstrom Excavation & Blacktop Group.
• Regulatory: strict adherence to state labor, environmental, and safety statutes; utility notification at least 48 hrs prior to work.