This contract concerns the design‑build of drainage and roadway improvements on Sauk Prairie Road (site 31024) within Snohomish County, WA. The scope includes extensive earthwork, culvert installation, road‑base preparation, hot‑mix asphalt paving, erosion control, traffic‑control devices, and related ancillary works such as guardrails, signage, and temporary facilities. The county issued a formal bid (094‑19) with a submission deadline of 14 Jan 2020; the engineer’s estimate was $870,000, and the award was made to Reece Construction on 3 Mar 2020. The contract is a standard public‑works competitive bid requiring a 5 % bid bond and compliance with Washington wage‑payment statutes, non‑collusion, and recycled‑material requirements.
• Scope: drainage, excavation, culverts, pavement, erosion control, traffic safety.
• Awarded to: Reece Construction (single‑vendor award).
• Key dates: bid due 14 Jan 2020, award 3 Mar 2020.
• Budget: engineer’s estimate $870 k; winning bid near that amount.