The West Side Tanks and Pump Station Project involves the construction of two new six million gallon pre-stressed concrete water storage tanks, a new concrete masonry unit (CMU) block Booster Pump Station building and equipment, and other structural, mechanical, and electrical ancillary systems. The project is being awarded to Auburn Constructors, LLC, pending City Council approval. The engineer's estimate of probable cost is $23,000,000.
• The project includes the construction of two new water storage tanks and a booster pump station.
• The project also includes site grading and paving, storm water treatment basins, and electrical site work.
• A pre-bid conference was held on December 11, 2019, at the Pleasant Grove Wastewater Treatment Plant.
• The bid submission date was January 30, 2020.
• The project is being awarded to Auburn Constructors, LLC, pending City Council approval.