The contract is for the construction of Willow Heights Booster #95, which includes grading, underground utilities, erosion control, site restoration, and drainage. The project is expected to be completed by December 31, 2024. The bid was awarded to three vendors: Key Builders, Kramer, and Benike, with prices ranging from $254,392.00 to $309,579.00.
• The project involves construction work, including grading and underground utilities.
• The bid was submitted electronically through the Public Purchase website.
• The contract has a lump sum price of $300,575.00, with unit prices for certain items.
• The vendors are required to submit a bid bond and supporting instruments as part of their bid proposal.
• The contract has a completion date of December 31, 2024.