The contract is for the renovation of the existing 17,700 SF pool building to replace existing mechanical and electrical equipment. The work may also include items described in Section 012300 "Alternates" as additive alternates. The contract was awarded to Dawson Construction, LLC for a total bid of $4,058,200. The project is expected to start after the CBJ Assembly approves the award at the Regular Assembly Meeting on August 1, 2022. Key aspects of the contract include:
• Replacement of mechanical and electrical equipment
• Code required and functional improvements to the building's architectural layout
• Additive alternates for additional work
• Total bid of $4,058,200
• Award to be approved by the CBJ Assembly