The Forest Hills Water Main Rehabilitation project involves the construction of approximately 740 LF of 12-inch diameter C900 PVC restrained joint water main, 270 LF of 8-inch and 12-inch diameter ductile iron restrained joint water main, and other related work. The project includes excavation, dewatering, shoring, relocating existing utilities, and restoring surface conditions. The contract was bid on by several companies, with the lowest bid being $1,288,527.50. The project is located in Bellevue, WA, and the bid contact is Angela Carlson.
• The project involves the construction of new water mains and the relocation of existing utilities.
• The contract includes excavation, dewatering, and shoring work.
• The project requires the restoration of surface conditions, including asphalt trench patching and concrete sidewalks.
• The contract was bid on by several companies, with the lowest bid being $1,288,527.50.
• The project is located in Bellevue, WA, and the bid contact is Angela Carlson.