The contract is for the reconstruction of Sheridan Lake Road and a 20" water main between June Court and Rapid Creek. The project has an engineer's estimate of $2,220,000.00 and an advertising authority of $1,480,000.00. The contract was awarded to multiple vendors, including Mainline, Hills, RCS, and others. The scope of work includes the reconstruction of the road and the installation of a new water main.
• The project is located in Rapid City, South Dakota.
• The contract was awarded through a competitive bidding process.
• The vendors are responsible for completing the work according to the contract specifications and timelines.
• The contract includes provisions for payment, warranties, and guarantees.
• The City of Rapid City is responsible for overseeing the project and ensuring that the work is completed to their satisfaction.