This contract concerns a modest interior renovation of the Government Center Court Services building in Woodstock, Illinois. The work is divided into two phases totaling roughly 1,130 sq ft and includes demolition, new casework, finishes, mechanical, plumbing, electrical, and low‑voltage data installations while maintaining building occupancy. The procurement was conducted via an electronic bid process with a mandatory 10 % bid bond, performance and payment bonds, and compliance with Illinois prevailing‑wage requirements. The contract was awarded to a single general‑contractor, Efraim Carlson, at a low‑to‑mid‑six‑figure lump‑sum price. Key points:
• Scope: interior demolition, new workstation counters, break‑room and conference‑room build‑out, HVAC, plumbing, electrical, data, and finish work.
• Requirements: bid bond (≥10 % of bid), 100 % performance and payment bonds, insurance minimums, prevailing‑wage compliance, electronic PDF submission.
• Schedule: bid due August 1 2023 9:00 AM, bid opening via WebEx August 1 2023 1:00 PM, original construction timeline not disclosed.
• Regulatory: governed by McHenry County Purchasing Ordinance, AIA A201‑2017 contract, Illinois Prevailing Wage Act.