The contract is for the installation of a vault containing a flow meter, valves, and bypass pumping port at the District's existing Freegard Sewer Lift Station facility. The project includes the installation of a precast concrete vault, 8-inch DI sewer force main piping, and other associated appurtenances. The bids for the project were received at the offices of Sammamish Plateau Water, and the apparent low bidder is Westerlund Excavation, LLC. The engineer's estimate for the project is $100,000 to $120,000.
• The project includes the installation of a precast concrete vault and 8-inch DI sewer force main piping.
• The project requires the removal of two trees.
• The landscaping and fencing will be restored after construction.
• The bids for the project were received at the offices of Sammamish Plateau Water.
• The apparent low bidder is Westerlund Excavation, LLC.