The City of Bellevue is seeking a contractor to replace the Coal Creek Hill storm drainage pipe. The project includes the installation of approximately 213 LF of "butt-fused" storm drain HDPE pipe, connections to existing catch basin structures, modification of catch basin structures, removal and abandonment of storm pipe, erosion control, plantings, and restoration. The engineer's estimate for the project is $142,953.00. The contract was awarded to one of the bidders, but the document does not specify which one.
• The project requires the installation of storm drain HDPE pipe within a steep slope, which may require hand-dug trenching.
• The contractor must connect the new pipe to existing catch basin structures and modify them as necessary.
• The contractor must also remove and abandon the existing storm pipe and provide erosion control measures.
• The project includes plantings and restoration of the area.
• The engineer's estimate for the project is $142,953.00.