The City of Napa Utilities Department issued a Request for Proposals (RFP) for NVTA Sheehy Ct 36-Inch Replacement Construction Management. The purpose of the RFP was to select a consultant to provide construction management and inspection services for the transmission main replacement. The contract was awarded to Consolidated CM after a scoring committee evaluated five proposals from different firms. The project involves providing construction management for the removal of approximately 1700 feet of 36-inch asbestos cement pipe and the installation of approximately 1700 feet of 36-inch AWWA C200 steel cement lined and coated transmission main.
• The project is located in Napa County.
• The City of Napa Utilities Department is the agency responsible for the project.
• The contract was awarded on December 9, 2022.
• The scoring committee evaluated the proposals on December 8, 2022.
• Five proposals were submitted by different firms, including Alpha CM, Consolidated CM, Consor North America, Inc., Kleinfelder Construction Services, Inc., and Willdan Engineering.