The contract is for the Coal Creek Culvert Roughened Channel Repair project, which involves the installation of a temporary water diversion system, removal of an existing concrete sill, excavation of large boulders, and construction of a roughened channel using import large boulders and salvaged boulders. The project also includes the restoration of grades along the bank and staging area, and the revegetation of the riparian corridor. The contract was awarded to Mike McClung Construction Co. and Road Construction Northwest, Inc. The bid tabulation shows the itemized costs for each company, with a total cost of $152,692.83 for Mike McClung Construction Co. and $648,835.00 for Road Construction Northwest, Inc.
• The project involves the installation of a temporary water diversion system
• The project involves the removal of an existing concrete sill
• The project involves the excavation of large boulders
• The project involves the construction of a roughened channel using import large boulders and salvaged boulders
• The project involves the restoration of grades along the bank and staging area
• The project involves the revegetation of the riparian corridor