The contract is for JOC Citywide Civil/Site Work, specifically for 24" water line potholing at 152nd and Van Buren. The project involves construction and site investigation. The contract was awarded to Talis Construction Corporation, and the project manager is Timothy Boyer. The contract has a duration of 90 days and a contract amount of $12,499. The contract includes a change order for a no-cost time extension.
• The contract is for a specific construction project
• The project involves water line potholing
• The contract has a duration of 90 days
• The contract includes a change order for a no-cost time extension
• The contract amount is $12,499