The County of Orange has awarded a contract to Sukut Construction, LLC for the OAL Landfill Gas Header Upgrade Phase 1 project. The project involves the installation of temporary jumper lines, abandonment, and connection of various Landfill Gas (LFG) lines, trenching and fill of LFG lines, utility crossings, and paving repairs. The contract price is $2,496,540, and the project is expected to be completed within 112 calendar days. The contract includes provisions for bonds, insurance, and liquidated damages. The County has designated a Project Manager to oversee the project, and the Contractor is required to provide a superintendent to be present on site at all times.
• The project includes the installation of various LFG lines and equipment, such as 6-inch, 8-inch, 12-inch, 18-inch, and 30-inch solid HDPE pipes.
• The project requires the Contractor to provide a Faithful Performance Bond and a Labor and Material Payment Bond, each in an amount equal to 100% of the Contract Price.
• The Contract includes provisions for liquidated damages in the amount of $1,800 per day for each calendar day that completion of all the work required by the Contract Documents is delayed beyond the Contract Time.
• The Contractor is required to perform at least 51% of the work with its own organization.
• The Contract includes provisions for change orders, claims, and disputes.