The contract is for the rehabilitation of the Woodward Pond Dam, which includes earthmoving, concrete work, construction of a new box culvert, and replacement of outlet works. The engineering estimate for the project is $1,474,000.00, and the contract was awarded to Luciano Excavating Inc. for $1,456,300.00. The project will be funded by the City of Keene's CIP budget. Key aspects of the contract include:
• Rehabilitation of the Woodward Pond Dam
• Earthmoving and concrete work
• Construction of a new box culvert
• Replacement of outlet works
• Funding from the City of Keene's CIP budget