The contract is for the Interim North Lake Lift Station Capacity Improvements project, which includes the installation of new pumps, a standby generator, and other equipment. The project also includes construction of a new building to house the generator and electrical equipment, as well as modifications to the existing electrical building. The estimated cost of the project is $3,500,000. The scope of work includes mobilization, cleanup, and demobilization, survey, locate existing utilities, temporary erosion and sediment control measures, traffic control, salvage and demolition, temporary bypass pumping, shoring and earthwork, unsuitable excavation, modifications to existing facilities, new dry well, pumps, and piping, generator building and equipment, odor control room and equipment, modify existing electrical building, fencing and gates, HVAC, electrical, pre-purchased equipment coordination, HMA, and landscaping.
• The project is located within the City of Sammamish, King County, Washington.
• The bid documents shall be combined in a single, electronic PDF formatted file, and uploaded to Public Purchase.
• A non-mandatory pre-bid on site visit was held on April 17, 2023.
• The apparent low bidder is McClure and Sons, Inc. with a total bid of $4,349,706.00.
• The second award is Second Award Construction, Inc. with a total bid of $4,537,500.00.