Coastal Carolina University's Procurement Services department issued a Request for Quote (RFQ) for the removal and replacement of ChampionWall panels at the university's baseball stadium. The contract was awarded to Custom Designs Marine Contracting Inc for a total value of $52,727.80. The scope of work includes removing the existing panels and replacing them with new ones, as specified in the provided documentation. Key points to consider include the requirement for a Certificate of Insurance (COI) prior to commencement of services and the protest procedure outlined in the South Carolina Code of Laws.
• The contract has a duration of approximately 22 days.
• The university reserves the right to protest the award of the contract.
• The contractor must provide a COI prior to commencement of services.
• The contract value is $52,727.80.
• The scope of work includes removing and replacing ChampionWall panels.