This municipal contract calls for the furnishing and installation of complete three‑way generator transfer switches at Fire Station #2 and Fire Station #3, with optional alternates for Fire Station #4 in the 2025 and 2026 contract years. The work includes delivery of the switch assemblies, associated wiring, testing, and commissioning to integrate with existing generator sets. Bids were received on May 30 2025, and the bid tabulation lists unit prices ranging from approximately $15 k to $63 k per switch. No award decision is disclosed, and the agency’s contact details are not provided in the excerpt.
• Scope: Install three‑way generator transfer switches (one per fire station).
• Financials: Base‑bid total for stations #2 + #3 = $106,338 (extension $121,176); alternates priced $15,420–$28,858.
• Procurement: Open competition with bids submitted by at least two electrical contractors; agency is the City of Waukesha, WI.