The contract is for the demolition of the Front Steps building structure, which is part of the Irishtown Bend hillside stabilization project. The project includes hazardous material abatements and removal of the vacant multifamily residential structure. The engineer's estimate for the project is $265,000, but Baumann Enterprises, Inc. was awarded the contract with a bid of $209,444. The project is a partnership between Cleveland Metroparks, Riverbed West, LLC, and the City of Cleveland.
• The project is for the demolition of a building structure
• The project includes hazardous material abatements
• The project is part of the Irishtown Bend hillside stabilization project
• The engineer's estimate for the project is $265,000
• Baumann Enterprises, Inc. was awarded the contract with a bid of $209,444