This contract covers the complete demolition, renovation, and upgrade of the Skagway Well House #2, including removal of an existing generator and fuel storage tank, installation of a new 125 kW standby diesel generator with automatic transfer switches, associated electrical upgrades, civil earthwork, and a chain‑link fence. The scope also mandates a temporary 125 kW generator during transition and limits well‑house downtime to two days, requiring an emergency response plan for longer shutdowns. The project is funded entirely by the Municipality of Skagway and is awarded on a firm‑fixed‑price basis.
• Demolition of existing generator, ATS, fuel tank, and related utilities.
• Supply and install a new 125 kW standby generator, ATS, and required electrical distribution.
• Civil work: concrete slab, back‑fill, grading, and chain‑link fence installation.
• Tight outage limits (2‑day maximum) with mandatory emergency‑response planning.
• Fixed‑price, not‑to‑exceed contract valued at $386,300, with performance and payment bonds equal to 100 % of the bid.