The City of Spokane Parks & Recreation Department contracted the renovation of the Downriver Golf Course cart‑path system (Phase 1). The scope includes demolition of existing asphalt cart paths and parking areas, installation of a new boulder retaining wall, new curbing, hot‑mix asphalt paving, landscape and irrigation repairs, and optional staging‑area alternate. The work is divided into Phase A (hole #18) and Phase B (remaining areas) with tight seasonal scheduling to avoid disruption of the golf season. The contract was awarded on a lump‑sum basis to Zetin Contractors, who must provide a 5 % bid bond, performance and payment bonds equal to 100 % of the contract price, meet prevailing‑wage and MBE/WBE goals, and maintain extensive insurance and safety compliance.
• Base‑bid items: demolition, retaining wall, new curbing, asphalt paving (~14,850 sf), landscape/irrigation work.
• Schedule: Phase A complete by 22 Nov 2024; Phase B complete by 16 May 2025; contractor must start within 10 days of notice to proceed.
• Mandatory requirements: 5 % bid bond, 100 % performance/payment bonds, one‑year guarantee, liquidated damages of $750/day, insurance limits of $1 M (general, auto, umbrella) plus workers’ compensation.