All Pro Asphalt & Bettis Asphalt & Maintenance LLC
Construction, Inc.
Description
This contract is for the asphalt replacement at three locations: Quincy Elementary School, French Middle School, and Williams Magnet School. The contract includes base bids and add alternate scopes of work for each location. The total bid amount for the contract is $266,106.00, and the total awarded amount is $159,795.00. The contract includes work such as milling and overlaying, removing and replacing chain link fences, and replacing curb islands. The contract also includes an allowance for unforeseen work.
• The contract is for asphalt replacement at three locations
• The contract includes base bids and add alternate scopes of work
• The total bid amount is $266,106.00
• The total awarded amount is $159,795.00
• The contract includes work such as milling and overlaying, removing and replacing chain link fences, and replacing curb islands