The City of Spokane contracted the renovation of the North pedestrian suspension bridge in Riverfront Park, including structural steel repairs, concrete deck replacement, drainage upgrades, illumination system upgrades, and associated site work. The project is a full‑scope bridge refurbishment executed under a lump‑sum award to a single contractor, with a design‑build style package supplied by the city and its engineering consultants.
• Scope covers bridge deck removal, steel member repair (types 1‑7), railing retrofit, vault‑lid reconstruction, and utility conduit installation.
• Mandatory pre‑bid conference (Mar 12 2021) and a 180‑working‑day construction schedule after Notice to Proceed.
• Engineer’s estimate roughly $2.3 M; award lump‑sum price $2,129,949.