The contract is for the Cathedral Drive Panel Repair and ADA Improvements project, which includes concrete pavement rehabilitation, panel replacement, spall repair, spot repair of curb and gutter, and joint resealing. The project also incorporates sidewalk ADA improvements at intersections along Cathedral Drive from Regional Way to 3rd Street. The engineer's estimate for the project is $628,241.60, and the advertising authority is $610,000.00. The bidders for the project are JV Bailey, Complete Concrete, and Tru Form Construction, with bids ranging from $742,308.95 to $865,698.60.
• The project includes concrete pavement rehabilitation and ADA improvements.
• The engineer's estimate for the project is $628,241.60.
• The advertising authority is $610,000.00.
• The bidders for the project are JV Bailey, Complete Concrete, and Tru Form Construction.
• The bids for the project range from $742,308.95 to $865,698.60.