The County of Sacramento is seeking a contractor to replace an existing equipment lift with a new one at the North Area Recovery Station. The contract includes the furnishing of all labor, materials, and equipment for the replacement of the equipment lift and other incidental work. The estimated construction cost is $125,000, and the contractor must have a General Engineering Contractor, Class A license. The contract was awarded to Air & Lube Systems, Inc. with a total bid of $150,846.00.
• The contract includes the replacement of an existing equipment lift with a new one.
• The contractor must have a General Engineering Contractor, Class A license.
• The estimated construction cost is $125,000.
• The contract was awarded to Air & Lube Systems, Inc. with a total bid of $150,846.00.
• A pre-bid conference was held on December 2, 2021, at 10:00 am at the North Area Recovery Station Equipment Maintenance Facility.