The contract is for the construction of Navigation Boulevard Up River to Leopard Street in Corpus Christi, Texas. The project includes the installation of rigid concrete pavement, marking and signage improvements, storm water drainage improvements, water distribution improvements, and wastewater improvements. The contract also includes additive alternates for electrical conduit, early project completion, and a 24" wastewater effluent force main. The total awarded scope of work is approximately $19,130,549.05.
Key aspects of the contract include:
• The project involves the construction of a 60' back-to-back curb
• The contract includes a base bid and additive alternates
• The base bid includes parts A to H, covering various aspects of the construction project
• The additive alternates include electrical conduit, early project completion, and a 24" wastewater effluent force main
• The contract has a total awarded scope of work of approximately $19,130,549.05