This contract involves the supply, installation, and commissioning of an automated cantilever slide gate system at Crystal Lake Park, Manchester, NH. The City of Manchester awarded the $29,045 contract to Fences Unlimited to deliver the gate, install the hardware, provide the motor/operator, and train city personnel. The scope excludes all electrical service work, which will be performed by a separate contractor, and includes site preparation, trenching, and post‑installation restoration. The project must be completed within a 30‑day construction window, with specific milestones for gate installation (July 31‑August 31) and operator installation (September 14‑28).
• Scope: Provide and install a 4 ft × 28 ft cantilever slide gate, 1 hp motor, safety devices, and related hardware.
• Exclusions: Electrical service, trenching, and permitting are not part of this contract.
• Schedule: Gate work July 31‑August 31 2026; operator work September 14‑28 2026; total project duration ~59 days.