This contract is for the replacement of a chair lift at Landon Middle School. The contract was awarded to AEL, Inc. for a total bid of $48,250.00. The scope of work includes the removal and replacement of the chair lift, with acceptable manufacturer/models being Garaventa GSL-1 Artira or Savaria Omega or equal. The project is being managed by Topeka Public Schools, with Deana Merryman listed as the bid contact.
• The contract is for a lump sum payment of $48,250.00.
• The project requires the removal and replacement of the chair lift.
• The acceptable manufacturer/models are Garaventa GSL-1 Artira or Savaria Omega or equal.
• The project is being managed by Topeka Public Schools.
• The bid contact is Deana Merryman.