The Downtown Bridges and Trail Improvement Project, Phrase I, involves clearing and grubbing, stream bank restoration, removal of an existing building, relocation of a storage container, and minor roadway excavation. The project has an engineer's estimate of $108,000.00. The contract was awarded to Pro Builders, with the intention of recommending City Council approval. Key aspects of the project include:
• Clearing and grubbing
• Stream bank restoration
• Removal of an existing building
• Relocation of a storage container
• Minor roadway excavation
• Engineer's estimate: $108,000.00
• Contract award to Pro Builders
• City Council approval recommended