The contract is for the rehabilitation of the Water Pollution Control Plant's primary effluent pump station, which includes rebuilding or replacing identified vertical turbine pumps, swing check valves, and isolation butterfly valves. The project has an expected duration of approximately 280 calendar days and an estimated total bid price of $410,000. The successful bidder must provide proof of registration with the California Department of Industrial Relations and pay not less than the prevailing rate of per diem wages. Some key points about the job's work and scope-of-work include:
* Rebuilding activities may include replacement of specific pump and valve components such as gaskets, seals, bearing, shafts, and/or impellers.
* The specific pump and valve repairs shall be completed by qualified technicians.
* The overall schedule of events must comply with owner requirements, as specified in this contract.
* The project is subject to compliance monitoring and enforcement by the California Department of Industrial Relations.
* The contractor must submit certified payroll records to the Labor Commissioner.
* A pre-bid conference was held on March 27, 2024, at 1:00 PM EDT, and attendance was mandatory for bidders.
Some other key points include:
* The contract was awarded to PumpMan NorCal.
* The bid opening date was April 12, 2024, at 2:00 PM.
* The contract has a 5% local vendor preference.
* The contractor must provide a bid bond in the amount of 10% of the bidder's maximum bid price.