This contract upgrades the Kwigillingok village electric distribution system, replacing aging overhead components, installing new poles, conductors, transformers, and street‑lights, and providing full material and labor services. The Alaska Energy Authority (AEA) funded the project, and after an open competition the contract was awarded to Hotwire LLC. The work includes site investigation, demolition of existing infrastructure, installation of H‑pile foundations, pole erection, conduit and conductor placement, transformer replacement, and comprehensive testing and commissioning, all under state wage‑rate and safety requirements.
• Scope: Complete overhaul of the rural power distribution network (materials, labor, equipment, and commissioning).
• Schedule: Bids closed 24 Feb 2017; substantial completion required by 31 Aug 2018; final completion by 2 Oct 2018.
• Procurement: Full‑open competition, lump‑sum (firm‑fixed‑price) award to Hotwire LLC; bid security 5 % and performance/payment bonds required at 100 % of contract price.