This contract involves the demolition of an existing plate‑heat‑exchanger system at the Plymouth Cultural Center Ice Rink and the installation of a new heat‑exchanger unit together with all associated mechanical, electrical, and control equipment, piping, gauges, and related accessories. The City of Plymouth issued an open sealed‑bid solicitation, received two bids, and awarded the contract to Shaw Construction Management Co. for a lump‑sum price. The work must begin no earlier than 19 May 2025 and be completed by 18 July 2025, with a one‑year warranty and required testing & balancing.
• Scope: demolition, new heat‑exchanger installation, complete mechanical‑piping‑gauge package, testing & balancing, start‑up manuals, and warranty.
• Schedule: bid deadline 4 Apr 2025, bid opening 17 Apr 2025, start 19 May 2025, finish 18 July 2025.
• Award: Shaw Construction Management Co. awarded at $87,996 (lowest compliant bid).