This contract is for the removal of pipe insulation and the re-insulation of the existing chilled water supply and return piping at Hope Street Academy. The contract was awarded to Capital Insulation Inc for a total of $42,209.00. The scope of work includes the removal of old insulation and the installation of new insulation, including fiberglass and armaflex. The contract also includes several alternate bids for different types of insulation and piping.
• The contract includes a base bid for the 1st floor/fiberglass insulation
• The contract includes several alternate bids for different types of insulation and piping, including armaflex and PVC jacket
• The contract includes a bid for the replacement of valves
• The contract has a total award value of $42,209.00