This contract awards the City and County of Denver Department of Transportation and Infrastructure a one‑year, $1.80 M project to rehabilitate approximately 38,000 linear feet of deteriorated sewer pipe using cured‑in‑place pipe (CIPP) and/or fold‑and‑form methods. The work includes video inspection, pipe cleaning, trenchless lining, grinding, tap cutting, seal‑kit installation, traffic control, laboratory testing, and mobilization. The contract was competitively bid, with Insituform Technologies, LLC selected as the lowest compliant bidder. The project must meet a 10 % MWBE participation goal and follows standard city prevailing‑wage requirements.
• Scope: 8‑, 10‑, and 12‑inch sewer pipe rehabilitation (CIPP/FFP) plus ancillary services.
• Value: $1,796,182.40 (awarded); engineers’ estimate $1,914,429.00.
• Timeline: Awarded Dec 2023, 365‑day performance period, with bid opening Aug 2023 and pre‑bid meetings in July 2023.