This contract concerns comprehensive upgrades to the Sludge Processing Building at the Hartford Water Pollution Control Facility. The work includes construction of a new Continuous Emission Monitoring System (CEMS) room, installation of new HVAC systems for existing and new CEMS rooms, replacement of HVAC equipment and controls, hazardous material abatement, coating removal, structural modifications to incinerator stacks, safety railing improvements, and associated electrical upgrades. The project requires full labor, equipment, permits, and materials, and mandates that the successful bidder hold a current DAS Contractor Pre‑qualification Certificate for water‑treatment plants and submit a 10 % bid security. A mandatory pre‑bid conference and site tour were held on February 13 2024.
• Scope: New CEMS room, HVAC upgrades, hazardous abatement, structural and electrical improvements.
• Location: Hartford, Connecticut – Hartford Water Pollution Control Facility (240 Brainard Rd).
• Procurement method: Invitation to Bid (ITB) with full open competition; award announced 5/24/2024.
• Requirements: DAS Contractor Pre‑qualification, 10 % bid security, compliance with CT state statutes.
Attached files
The award documents live at the source — open the contract source above to download them.