This contract involves the complete reconstruction of runway lighting and signage on Runway 6‑24 at Ann Arbor Municipal Airport. The scope includes removal of existing lighting and signs, installation of new medium‑intensity LED edge and threshold lights, new taxiway guidance signs, extensive underground electrical conduit and cabling, and all associated civil and electrical work. The work is funded by federal FAA AIP/IIJA and state MDOT grants, with the City of Ann Arbor handling procurement and contract administration. The project must be completed within a 40‑day calendar period (originally 35 days) once a Notice to Proceed is issued, and strict FAA safety and phasing plans must be followed.
• Scope: 44 new runway edge lights, 16 threshold lights, 12 guidance signs, plus conduit, HDPE, PVC, and electrical junctions.
• Schedule: Bids due 17 Sep 2026; construction anticipated to start Fall 2027; total contract duration 40 calendar days.
• Requirements: 5 % bid bond, performance & labor‑material bonds, prevailing‑wage compliance, detailed safety and FOD plans, FAA/MDOT coordination.