The Eastbank Hatchery project at Rocky Reach Dam was a construction contract overseen by Public Utility District No. 1 of Chelan County, Washington. The solicitation (No. 89‑01) called for labor‑and‑materials services to build a fish hatchery facility, with an agency‑estimated budget of $4.56 million. After public bid opening on 8 Feb 1989, the contract was awarded to IMCO General Construction, Inc. for a total of $3.44 million, indicating a competitive, below‑estimate award. The procurement followed a full and open competition process, required performance bonds from all bidders, and was classified as a Labor & Materials solicitation. The contract is a single‑award, lump‑sum construction effort focused on civil/structural work for hatchery infrastructure.
• Scope: Construction of a fish hatchery (civil works, concrete structures, water intake, mechanical/electrical systems).
• Budget: Agency estimate $4.56 M; award $3.44 M.
• Procurement: Open competition, performance bond required, award to IMCO General Construction, Inc.
• Timeline: Bid opening 8 Feb 1989; no explicit start or finish dates provided.