The contract is for the 2020-21 Sewer Rehabilitation project, which involves pipe bursting, trench excavation, and installation of new sewer pipes. The project is divided into several schedules, each with its own set of tasks and estimated costs. The contract was awarded to K&R Plumbing Co. Inc. and Emery & Sons Construction Group, LLC, with a total base bid amount of $665,047.00 and a total additive amount of $129,005.00. The contract includes various tasks such as mobilization, temporary traffic control, landscape restoration, and asphaltic concrete trench patch. The project requires the contractors to have minimum field experience for HDPE pipe bursting installation of three successfully completed projects totaling a minimum of 2,000 linear feet of mainline using the proposed pipe bursting technology.
• The contract involves pipe bursting and replacement of existing sewer pipes with new HDPE pipes.
• The project requires the contractors to have minimum field experience for HDPE pipe bursting installation.
• The contract includes various tasks such as mobilization, temporary traffic control, landscape restoration, and asphaltic concrete trench patch.
• The project is divided into several schedules, each with its own set of tasks and estimated costs.
• The contract was awarded to K&R Plumbing Co. Inc. and Emery & Sons Construction Group, LLC.