This contract is for the installation of stretched-fabric wall system acoustic panels at the County of Orange's facilities. The contract was awarded to C E Pickup Company Inc. dba Pacific Sound Control for a total of $64,746. The work includes providing all labor, materials, and equipment necessary for the installation. The contract duration is 120 calendar days from the effective date of the Notice to Proceed. The County of Orange reserves the right to enter and install equipment within each portion of the project as it is ready to receive same. The contractor is responsible for correcting any defective workmanship or materials.
• The contract includes a liquidated damages clause, where the contractor agrees to pay $500 per day for each calendar day that completion of all the work required by the contract documents is delayed beyond the contract time.
• The contractor is required to provide a Faithful Performance Bond and a Labor and Material Payment Bond, each in an amount equal to 100% of the contract price.
• The contract includes a provision for changes to the contract, where the contractor may submit a request for a change order, and the County may approve or reject the request.
• The contract includes a provision for termination, where the County may terminate the contract for convenience, and the contractor may be entitled to payment for work completed prior to termination.