The City of Leesburg, Florida, awarded a contract to Estep Construction, Inc. for the Lake Griffin Storm Water Improvements project. The project involves the construction of a wet detention pond, installation of an outfall structure, and other related work. The contract was awarded after a competitive bidding process, and the total base bid amount was $440,119.55. The contract duration is 180 calendar days. The project requires the contractor to provide labor, materials, equipment, and supervision related to the construction of the storm water improvements.
• The contract includes the construction of a wet detention pond
• The contract includes the installation of an outfall structure
• The contract includes the replacement of two pond outfalls
• The contract requires the contractor to provide labor, materials, equipment, and supervision
• The contract duration is 180 calendar days