The 2015 Sidewalk Safety Program is a construction project that involves the removal and replacement of Portland Cement Concrete (PCC) sidewalks in Corvallis, Oregon. The project requires the contractor to provide all necessary services, labor, materials, and equipment to complete the work. The project is expected to be completed by August 31, 2015. The bid tabulation shows that two companies, GT General Contracting and Brown Contracting, Inc., submitted bids for the project. The key aspects of the project include:
• Removal and replacement of PCC sidewalks
• Saw-cutting and other related construction
• Completion of the project by August 31, 2015
• Bid tabulation showing two bidders, GT General Contracting and Brown Contracting, Inc.