The contract is for a pavement rehabilitation project on Sage Avenue and Sycamore Street in Rapid City, South Dakota. The project involves replacing poly-b service lines and resurfacing streets. The bid summary section lists several companies that submitted bids for the project, including Hills Materials Company, Simon Contractors of SD, Inc., and Knife River-Rapid City. The engineer's estimate for the project is $250,000.
• The project is part of the City of Rapid City's capital improvement program.
• The bid submission date was July 15, 2014.
• A pre-bid conference was held on July 8, 2014.
• The bid summary section lists the bids submitted by each company, including the base bid and alternate bids.
• The contract was awarded to the lowest bidder, but the exact award amount is not specified in the provided text.