This contract covers the complete resurfacing of Buffalo Trail, Barron Court, and Green Lake Pass along with extensive utility upgrades. The scope includes excavation, replacement of sanitary and storm sewer mains, water‑main relocation, underground utility relocation, curb and gutter reconstruction, sidewalk replacement, asphalt paving, installation of traffic‑control devices, and comprehensive erosion‑control measures. The work is to be performed under a Best‑Value framework with a lump‑sum contract amount of $1.206 million, with a tight construction schedule of roughly four months.
• Primary work: street resurfacing, storm‑sewer and sanitary‑sewer pipe installation, utility relocation, and curb‑gutter replacement.
• Required coordination with city water, gas, electric, and telecommunications utilities; mandatory pre‑construction notification and daily traffic‑control plans.
• Contract includes stringent erosion‑control, daily street‑cleaning, and ADA‑compliant curb‑ramp construction, with retention held until final acceptance.